At this point we are settled and done with the first guy. The amount remaining unpaid was sufficient to cover the repairs needed on the patio and bridge. I’m struggling with what to do regarding the second. To be honest I’ve always been a bad judge of character, but I like the guy and have...
Since the terms of the contract don’t say in writing that draws were to be paid on a timed schedule as opposed to a completion schedule does that give us something to stand on legally if we tried to get payment for work not done back?
First contractor finished the job but we had withheld 10% upon satisfactory completion. The original job was to build the entire structure as a watertight exterior shell, unfinished interior, and put in a driveway (tiling the patio was not part of not). The only part not finished...
I live in Texas and have contracted a General contractor to perform some renovations/repairs to a casita attached to my house. This is a project that was started by another contractor and left finished sub par and leaking. We hired the new contractor to demo and repair the existing leaks on an...